Homeless Emergency Aid Program

 Project approved by Board of Supervisors on November 19, 2019, item 3.33  Authorization for EDA to provide oversight to the purchase of three residences by the Social Worker Action Group in Lake Elsinore, Wildomar, Perris or the unincorporated areas of District 1.  Offer made on 45011 Carla Court, Lake Elsinore – Receiving feedback from city of Lake Elsinore.  SWAG no longer moving forward on 45011 Carla Court, Lake Elsinore, due to input from the city of Lake Elsinore.  SWAG touring the property located at 18470 Grand Avenue, in the unincorporated area of District 1. SWAG states they have the support of the First District Supervisor to move forward on an acquisition of this property. Seeking First District's opinion on this.

Transportation Project: Cajalco Safety Project

 Total of 24 properties in project.  Right of Way Certification approved by Caltrans.  Temporary Construction Easements are expiring before construction commences. In process of obtaining an Amendment to TCE’s

Transportation Project: Temescal Canyon Road Widening (Dos Lagos)

 Total of 19 properties in project.  All offers presented.  14 completed and closed escrow.  5 in litigation (continuing negotiations).

 Notice of Intention to Adopt Resolution of Necessity approved on February 6, 2018.  Public Hearing to Adopt Resolution of Necessity approved on March 13, 2018.  1 Titan Billboard – Offer presented and settled. In process of obtaining signatures from Titan billboard.  Offer to Temescal Leroy accepted and received signed agreements. Form 11 in process with the Titan Billboard agreement.  Construction in process.  NexStar requested Transportation construct retaining wall, Transportation settled with owner for $65,000, Settlement Agreement in process.

Transportation Project: Temescal Canyon Road Widening (Dawson Canyon)

 Total of 10 properties in project.  All offers presented.  2 donations completed and closed escrow.  7 completed and closed escrow.  1 in litigation (continuing negotiations).

 Notice of Intention to Adopt Resolution of Necessity on approved on February 6, 2018.  Public Hearing to Adopt Resolution of Necessity approved on March 13, 2018.  Construction in process.

Transportation Project Orange Avenue Paving and Road Widening  Project 1 property in project  Offer Presented