First District Update_Feb 2020

• Multi-prime project delivery by Prowest Constructors, construction value $9,870,447. • Site sewer is now complete. Exterior wall framing, interior wall framing, overhead plumbing, overhead HVAC, and overhead electrical are all in progress. • Construction began July 15, 2019 and is expected to be completed February 2021.

Woodcrest Library Community Room Expansion

• Woodcrest Library was constructed in 2007 and is in the unincorporated community of Woodcrest at 6625 Krameria Ave. The project will add approximately 2,200 sq. ft. to the existing library and renovate an additional 3,000 sq. ft. which will double the size of the existing community room, renovate the children’s area, expand the existing library collection floor, and allow the Woodcrest Library to offer residents greater access to the library’s classes and programs. • A project budget of $2,499,025 and award of the Vincor construction agreement was approved by Board of Supervisors on August 6, 2019. • Library closed on August 7, 2019. Start of construction August 21, 2019 and demolition commenced on August 26, 2019. • Project will now be constructed in one phase with completion scheduled March 31, 2020. Expect full occupancy four weeks later, after the furniture, computers and staff have setup the new spaces. • Provide site planning and design for phased construction of improvements to Lakeland Village Community Center including, but not limited to; landscaping, pavement removal, athletic field rehabilitation, playgrounds, recreation activities, ADA upgrades, water quality, and parking and building upgrades. Current scope focusing on design on approximately five acres of the property. Future phases of the project will be determined by budget and funding. • Design development costs of $335,027 and a consultant agreement with Rick Engineering approved by Board of Supervisors on June 4, 2019. • On December 17, 2019 BOS approved budget revision and approval of ezIQC contractor Vincor. • Construction expected to commence late January 2020.

Lakeland Village Community Center Master Planning Project

Made with FlippingBook - professional solution for displaying marketing and sales documents online