First District Update_Feb 2020
COMMUNITY DEVELOPMENT BLOCK GRANT
CDBG, HOME, and ESG Programs
• Staff are reviewing 2020-2021 CDBG District applications, Cooperating City applications, and ESG applications. Public Hearing for Proposed 2020-2021 Action Plan is scheduled for February 11, 2020. • Federal FY 2020 budget approved 12/22/19. The CDBG program received small increase over FY 2019. The County’s actual 2020-21 CDBG allocation to be determined by HUD in February- March 2020.
Home Enhancement Program
• Program provides up to $25,000.00* to low-income homeowners for eligible exterior repairs/improvements. o District 1: 3
▪ Good Hope – (1) JOB ▪ Mead Valley – (1) JOB ▪ Lake Elsinore – (1) JOB
• The Home Enhancement Program is marketed, through neighborhood canvassing flyers dropped off at Community Centers and Libraries, referrals from previous clients, and discussions that come up at Community meetings.
Project Status Codes
APP
CC
Application
County Counsel
JOB
SCH
Job Walk
Scheduled for Construction
BP
CON
Bid Process
Construction
AG
PC
Agreement
Project Completed
*Pre-1978 Program provides up to $35,000.00 to low-income homeowners for eligible exterior repairs/improvements in homes built before 1978.
Lakeland Village Community Center
• CDBG funds will be used to pay a portion of the total A/E expenses for the facility upgrade. PMO to submit payment request.
Day Street and Elmwood Road Improvements (Mead Valley)
• Trans and EDA have completed CEQA and NEPA environmental reviews. Substantial Amendment adding the project to the 2019-20 Action Plan approved by Board on 9/10/2019. MOU was issued to Trans. Project estimate $252,000. Expect construction to begin in January.
Good Hope and Mead Valley
• The Grove is working with County Counsel regarding CDBG Sponsor’s Agreement language.